Pool & Spa Construction Project
a Backyard Renovation in Mesa, AZ

Click any image to view full size
Blue Light
Green Light
Purple Light



Before Construction


Excavation


Plumbing



Steel


Shotcrete


Boulders / Rock Waterfall


Flagstone


Deck Framing


Deck Concrete


Equipment Wall


Acrylic Decking


Palm Trees


Stucco & Paint


Landscape Lighting


Pebble Tec Finish


Landscaping Rocks


Completed




return to raktron.com


©2006 Raktron, Inc.


 









View the construction from 4 angles

View 1
View 2
View 3
View 4

 
• Raised Spa with Rock Waterfall
• Pebble Tec Interior
• 8' Deep End
• In-Floor Cleaning System
• Automated Wireless Controls
• SAM / SAL Color Lighting
• Acrylic Deck & Flagstone Coping
• Gas Heater (400kBTU)
• Genuine Rock Boulders
• 90' Perimeter, 19800 gal

Detailed Specifications

   Pool built by:
We believe the company that did our pool and spa is the best in the Phoenix Valley. If you live in the area and are considering a pool,
Contact Us and we will be happy to answer any questions, and tell you how you can end up with a better pool while spending less money.


   Masonry/Stucco: Brad Symolon

   Painting: Steve Rockwell (The Masters)
   
Palm Trees: Moon Valley
   Landscaping, Irrigation, Lighting & Sound: Owner

 
Done by Pool Company:
Layout: Feb. 21
Excavation: Feb. 23-24
Plumbing: Feb. 27-28, Mar. 7-8
Steel: Mar. 3-4, 6
Electrical: Mar. 7
Shotcrete: Mar. 13
Gas Line: Mar. 14
Boulders / Rock Waterfall: Mar. 17
Flagstone: Mar. 21-22
Deck Form/Concrete: Mar. 27-28
Deck Acrylic: Apr. 4-6
Cleanup: Apr. 10
Pebble Tec Surfacing: Apr. 19-20
Filled: Apr. 21
Final Startup: Apr. 22

Non-Pool Items:
Equipment Wall: Mar. 30-31
Outer Wall Repair, Stucco: Apr. 3-7
Palm Trees Planted: Apr. 11
Irrigation System: Apr. 12-16
Outdoor "Rock" Speakers: Apr. 12
Landscape Lighting: Apr. 14-17
Painting of Walls: Apr. 15
Landscaping Rocks (54 Tons): Apr. 19-20